Who is responsible to ensure detailed technical reviews of the system design are conducted?

The responsibility to ensure detailed technical reviews of the system design are conducted rests with the person who owns the acquisition and ensures the system’s technical integrity throughout the development process. This role—the Diving System Acquisition Manager—is accountable for defining requirements, coordinating design activities, and guaranteeing that thorough technical reviews are planned and completed before moving forward. They oversee risk, compliance with standards, and alignment with mission needs, making them the person who ensures these crucial reviews happen. The Diving System Program Manager handles program-level planning and execution, such as scheduling and coordinating across teams, but the explicit duty to initiate and ensure detailed design reviews lies with the acquisition manager. The On-site Surveyor focuses on field data and site conditions, not the formal review of the system’s design. The Quality Assurance Manager concentrates on process and product quality, not the primary ownership of initiating and validating design reviews.

The responsibility to ensure detailed technical reviews of the system design are conducted rests with the person who owns the acquisition and ensures the system’s technical integrity throughout the development process. This role—the Diving System Acquisition Manager—is accountable for defining requirements, coordinating design activities, and guaranteeing that thorough technical reviews are planned and completed before moving forward. They oversee risk, compliance with standards, and alignment with mission needs, making them the person who ensures these crucial reviews happen.

The Diving System Program Manager handles program-level planning and execution, such as scheduling and coordinating across teams, but the explicit duty to initiate and ensure detailed design reviews lies with the acquisition manager. The On-site Surveyor focuses on field data and site conditions, not the formal review of the system’s design. The Quality Assurance Manager concentrates on process and product quality, not the primary ownership of initiating and validating design reviews.